West Hollywood is juggling many construction projects all across town, and City Council will get their quarterly progress report when they meet on Monday night. Here’s a sneak peak at how the projects are coming along.
CRESCENT HEIGHTS PARKING LOT
LOCATION: 8120 Santa Monica Boulevard
Environmental remediation is complete, and crews have almost finished building out the lot that will provide 62 coveted parking spots to the neighborhood’s residents, businesses and customers, along with four EV charging stations. The parking lot is a temporary measure, and the lot will probably become something grander once City Hall decides what the grand plan is. The lot is expected to open during the first quarter of 2025.
FORMER PETE’S MAGNOLIA CLEANERS…