New Stanislaus County Courthouse 75% complete. Here’s what’s going to happen to the old one

The new Stanislaus County Superior Court building in downtown Modesto is nearly complete and beginning to join the city’s skyline, but it took more time and money than originally expected.

The project started with an estimated budget of $278.2 million over a decade ago. The current price tag is estimated at $351.9 million.

Plans for a new courthouse were proposed in 2000 but weren’t authorized until 2010. In September, The Modesto Bee reported it was slated to finish in February 2025.

https://img.particlenews.com/image.php?url=4Ol10l_0v9XpH9v00
The Stanislaus County Superior Court building under construction in Modesto, Calif., Thursday, Aug.22, 2024. Andy Alfaro/[email protected]

“There is still some work left to do on things like testing and validation of utilities connections; network integrating; and some framing, drywall, and other finishes,” wrote Blaine Corren, spokesperson for the Judicial Council of California — the proprietor of both the new and old courthouses…

Story continues

YOU MIGHT ALSO LIKE