Contractor crews with the Virginia Department of Transportation are scheduled to implement the continuous closure on the I-64 west general purpose lanes off-ramp to I-564 west to expedite bridge widening activities for the I-64 east bridge over I-564.
This lane closure is expected to be in place through late fall as part of construction for the first phase of the Hampton Roads Express Lanes Norfolk Segment. This is a continuation of the work that was paused earlier this spring to allow for peak summer travel traffic through the corridor.
While this closure will overlap with the current closures in the I-64 Reversible Express Lanes in Norfolk, performing this work concurrently allows the contractor to reduce the duration for the I-564 ramp lane reduction by nearly 10 weeks and minimize the overall duration of traffic impacts at this interchange…